BEV undertakes design, manufacture, testing, painting and certification of structures for offshore and onshore applications to AISC, API, IS or client standards. BEV has a team of competent design associates, design checker and draftsmen experienced in the field. Our design associates use STRAP or StaadPro software for design modelling and analysis, supplemented by custom developed spread sheets and Autocad for drafting. All materials of construction are chosen to meet code requirements, in particular, impact property and certification requirements (EN 10204 3.1 or 3.2). We have CNC profile cutters and flux cored arc welding machines, both manual and semi automatic.


Barring full penetration welds, all other welding is done using FCAW. We have an extensive range of WPQRs to ASME Sec IX, AWS D1.1 and EN 288 covering a wide range of materials, thicknesses and processes. We deploy welders and welding operators certified to Sec IX / EN 287 / AWS D1.1 by recognised third party certification agencies such as Bureau Veritas or TUV. We have a team of QC Inspectors and AWS/CSWIP 3.1/3.2 Certified Welding Inspectors. We have a fully enclosed steel grit blasting facility and air less spray painting facility. BEV is also fully equipped to carry out trial assembly of structures at its open lay down area. Non destructive testing such as radiography, ultrasound including TKY weld joints etc. and material testing at NABL accredited testing facility is available within reach.
Management team has extensive experience in the design and development, manufacture, testing, certification of large volume structures in the Middle East, especially with global oil and gas corporations and multi national service providers. In short, you are assured of a fully code compliant product and a truly world class service from India. For a list of structural work projects recently executed
| Parameter | Specification |
|---|---|
| Design Codes | AISC, API, IS, AWS D1.1, EN 288, client specifications |
| Applications | Offshore platforms, onshore structures, pipe racks, equipment supports |
| Design Software | STRAP, StaadPro, custom spreadsheets, AutoCAD |
| Welding Standards | ASME Sec IX, AWS D1.1, EN 288 |
| Fabrication Equipment | CNC profile cutters, FCAW machines (manual & semi-automatic) |
| NDT | Radiography, ultrasound including TKY weld joints, NABL accredited |
| Surface Treatment | Enclosed steel grit blasting, airless spray painting |
| Trial Assembly | Open lay down area for full trial assembly |
| Hot-Dip Galvanizing | Available through specialist facilities within reach |
| Client / EPC Contractor | End User | Equipment | Qty | Year |
|---|---|---|---|---|
| Siemens Ltd. | National Fertilisers Ltd | Procurement, fabrication and painting of Anchoring Base Frame for Process Gas Compressor GK2 for Panipat | 1 | 2011 |
| Siemens Ltd. | Bhushan Power & Steel Ltd | Procurement, fabrication, testing and Painting of Process Gas Piping-Meramandali | 1 | 2011 |
| Siemens Ltd. | Bhushan Power & Steel Ltd | Procurement, fabrication and painting of Anchoring Base Frame for Process Gas Compressor GK1 for Rengali 3 | 1 | 2011 |
| Siemens Ltd. | National Fertilisers Ltd | Procurement, fabrication and painting of Anchoring Base Frame for Process Gas Compressor GK2 for Bhatinda | 1 | 2011 |
| Daniel Measurement Solutions Pvt. Ltd., India | Oil And Natural Gas Corporation (Ongc) | Procurement, fabrication and delivery of Gas Compressor Shed in SS316 for ONGC's MHN Process Platform | 1 | 2011 |
| Siemens Ltd. | National Fertilisers Ltd | Procurement, fabrication and painting of Anchoring Base Frame GK2 for Nangal 1 | 1 | 2011 |
| Bodal Chemicals Ltd, India | Bodal Chemicals Pvt Ltd | Procurement, Fabrication & Testing of Pump Boot Frame. | 1 | 2010 |
| Kirloskar Pneumatic Co. Ltd., India | Oil And Natural Gas Corporation (Ongc) | Procurement, fabrication, machining and painting of Base Frames for LP Screw Compressors for MHN Process Platform, ONGC | 1 | 2010 |
| Bharat Heavy Electricals Ltd | Madhya Pradesh Power Generating Co. Ltd. | Procurement, Fabrication & Testing and Trial Assembly of 350 Tons of Boiler Columns for 2 x 600 MW Malwa Project | 1 | 2009 |
| Flsmidth Pvt Ltd, India | Saurashtra Chemicals | Fabrication of conveyor trestles for Saurashtra Chemicals Caustic Soda Revamp Project | 1 | 2009 |